To report the accomplishments of the project, you must apply Earned Value (EV) to the figures and calculations in the project. EV is the quantification of the “worth” of the work done to date.
In other words, EV tells you, in physical terms, what the project has accomplished. As with PV and AC, EV can be presented in a Cumulative and Current fashion.
18
65 reads
CURATED FROM
IDEAS CURATED BY
Self Motivated, Trauma Neutralizer, Lover of Persiflage & Communication!
Interested in being a certified PMP Project Manager? Follow me for curated information pertaining to the PMP certification.
“
Similar ideas to Earned Value (EV)
Our choice to work on a project is guided by how much we value finishing that project in that moment. Psychologists call this "subjective value."
Procrastination, psychologically speaking, is what happens when the value of doing something else outweighs the value of workin...
Deep work is a term developed by Cal Newport, stating that all intellectual activities should be performed in a state of distraction-free concentration that pushes your cognitive capabilities to their limit.
On the other side deep work is “half-work” or “shallow work”. That...
A survey of 122 senior executives from a variety of industries agreed that outside engagements were critical to leadership success now and in the future.
Meaningful engagement should be in activities that expose you to different people, information, and cultures, but is synergisti...
Read & Learn
20x Faster
without
deepstash
with
deepstash
with
deepstash
Personalized microlearning
—
100+ Learning Journeys
—
Access to 200,000+ ideas
—
Access to the mobile app
—
Unlimited idea saving
—
—
Unlimited history
—
—
Unlimited listening to ideas
—
—
Downloading & offline access
—
—
Supercharge your mind with one idea per day
Enter your email and spend 1 minute every day to learn something new.
I agree to receive email updates