Schedule Variance (SV) - Deepstash

Keep reading for FREE

Schedule Variance (SV)

Schedule Variance (SV)

Schedule Variance status does indicate the dollar value difference between work that is ahead or behind the plan and reflects a given measurement method.

Schedule Variance status does not address impact of work sequence.

The formula utilized to express schedule variance is project earned value minus the project planned value as of the date of examination.

*VERY IMPORTANT*

(SV = EV – PV) If the variance is equal to 0, the project is on schedule.

If a negative variance is determined, the project is behind schedule and if the variance is positive the project is ahead of schedule.

19

50 reads

MORE IDEAS ON THIS

What to remember about EVA...

Oftentimes the term “earned value” is defined as the “budgeted cost of worked performed” or BCWP.

This budgeted cost of work performed measure enables the project manager to compute performance indices or burn rates for cost and schedule performance, which provides...

18

149 reads

Cost Performance Index (CPI) Deeper Understanding Pt.2

Potential Causes of Favorable Cost Performance:

  • Efficiencies being realized
  • Work less complex than anticipated
  • Fewer revisions and rework
  • Favorable Market Fluctuations in the Cost of Labor or Material
  • Overhead Rate Decreases

...

18

49 reads

Summary of Earned Value Management (EVM)

  1. Organize the project team & the scope of work, using a work breakdown structure. Each task should have a single WBS number and organizational code.
  2. Schedule the tasks in a logical manner so that lower level schedule elements & the top level milestones.
  3. Allocate the total budg...

19

40 reads

EAC Deeper Understanding PT.2

  • Planned Value (PV) - How much work should be done?
  • Earned Value (EV) - How much work was done?
  • Actual Cost (AC) - How much did the work cost?
  • Budget at Completion (BAC) - What is the total job budgeted to cost?
  • Estimate at Completion (EAC) - What do we expect ...

19

35 reads

References:

Project Management Institute. (2004) A Guide to the Project Management Body of Knowledge (PMBOK® Guide). (Third ed.) Newtown Square, PA: Project Management Institute

Project Management Institute. (2005) Practice standard for earned value management (PMI Global Standard) (2005 ed.) Newtown S...

19

34 reads

Performance Indexes (PI)

Performance Indexes (PI)

Another analysis that can be done by using EVMS is that of Performance or establishing the project’s burn rate.

Two examination of performance are available to the project manager, Schedule Performance Index (SPI) and Cost Performance Index (CPI).

19

51 reads

Actual Costs (AC)

Actual Costs (AC)

Actual Cost (AC), also called actual expenditures, is the cost incurred for executing work on a project. This figure tells you what you have spent and, as with Planned Value, can be looked at in terms of cumulative and current.

  • Cumulative AC

19

77 reads

Earned Value (EV)

To report the accomplishments of the project, you must apply Earned Value (EV) to the figures and calculations in the project. EV is the quantification of the “worth” of the work done to date.

In other words, EV tells you, in physical terms, what the project has accompl...

18

58 reads

Cost Variance (CV)

Cost Variance (CV)

The cost variance is defined as the “difference between earned value and actual costs. (CV = EV – AC)” (PMI, 2004, p. 357)

Sometimes this formula is expressed as the difference between budgeted cost of work performed and actual cost work performed.

*VERY IMPORTANT*

19

45 reads

Cost Performance Index (CPI)

Cost Performance Index (CPI)

The CPI is defined by PMI’s PMBOK® Guide as a measure of cost efficiency on a project.

It is the ratio of earned value (EV) to actual costs (AC). The CPI is equal to the earned value divided by the actual costs, CPI = EV – AC.

Assuming your CPI efficiency remains the ...

18

39 reads

CHANCE REICHEL PMP

Originally published in part of 2006 PMI Global Congress Proceedings – Seattle WA

CHANCE REICHEL PMP

18

46 reads

Planned Value (PV)

Planned Value (PV)

Planned Value describes how far along project work is supposed to be at any given point in the project schedule and cost estimate.

PV, also known as Budget Cost of Work Scheduled (BCWS), can be defined as:

  • Define Scope: What you are tasked to do ...

18

88 reads

Estimates to Complete (EAC)

Estimates to Complete (EAC)

Anticipating future progress requires determining when the project will be completed and how much it will cost to complete it.

The Estimate at Completion (EAC) is the actual cost to date plus an objective estimate of costs for remaining authorized work.

The objective in preparing an E...

19

38 reads

What is Earned Value Analysis?

What is Earned Value Analysis?

Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports.

EVA provides a method that permits the project to be measured by prog...

20

247 reads

Variance Analysis (VA)

Variance Analysis (VA)

The PM will be provided with financial information from accounting that will expressed the actual cost incurred on the project's work is performed, then the PM will seek information from the team that will state the budgeted cost of work performed on the project, or earned value.

After thos...

18

56 reads

EVM Foundational Concepts

Earned Value Management Systems allow the project manager to answer the following three questions, as they relate to the project:

Where have we been?

Where are we now?

Where are we going?

In Earned Value Management, unlike in traditional manageme...

19

97 reads

Schedule Performance Index (SPI)

Schedule Performance Index (SPI)

The SPI is defined by PMI’s PMBOK® Guide as “a measure of schedule efficiency on a project.

It is the ratio of earned value (EV) to planned value (PV). The SPI is equal to earned value divided by planned value, SPI = EV/PV.

An SPI equal to or greater than one indi...

18

44 reads

CURATED FROM

CURATED BY

dennisanthony

Self Motivated, Trauma Neutralizer, Lover of Persiflage & Sapio-sensual

Interested in being a certified PMP Project Manager? Follow me for curated information pertaining to the PMP certification.

stash-superman-illustration

Explore the World’s

Best Ideas

200,000+ ideas on pretty much any topic. Created by the smartest people around & well-organized so you can explore at will.

An Idea for Everything

Explore the biggest library of insights. And we've infused it with powerful filtering tools so you can easily find what you need.

Knowledge Library

Powerful Saving & Organizational Tools

Save ideas for later reading, for personalized stashes, or for remembering it later.

# Personal Growth

Take Your Ideas

Anywhere

Organize your ideas & listen on the go. And with Pro, there are no limits.

Listen on the go

Just press play and we take care of the words.

Never worry about spotty connections

No Internet access? No problem. Within the mobile app, all your ideas are available, even when offline.

Get Organized with Stashes

Ideas for your next work project? Quotes that inspire you? Put them in the right place so you never lose them.

Join

2 Million Stashers

4.8

5,740 Reviews

App Store

4.7

72,690 Reviews

Google Play

samz905

Don’t look further if you love learning new things. A refreshing concept that provides quick ideas for busy thought leaders.

Sean Green

Great interesting short snippets of informative articles. Highly recommended to anyone who loves information and lacks patience.

Shankul Varada

Best app ever! You heard it right. This app has helped me get back on my quest to get things done while equipping myself with knowledge everyday.

Ashley Anthony

This app is LOADED with RELEVANT, HELPFUL, AND EDUCATIONAL material. It is creatively intellectual, yet minimal enough to not overstimulate and create a learning block. I am exceptionally impressed with this app!

Jamyson Haug

Great for quick bits of information and interesting ideas around whatever topics you are interested in. Visually, it looks great as well.

Laetitia Berton

I have only been using it for a few days now, but I have found answers to questions I had never consciously formulated, or to problems I face everyday at work or at home. I wish I had found this earlier, highly recommended!

Giovanna Scalzone

Brilliant. It feels fresh and encouraging. So many interesting pieces of information that are just enough to absorb and apply. So happy I found this.

Ghazala Begum

Even five minutes a day will improve your thinking. I've come across new ideas and learnt to improve existing ways to become more motivated, confident and happier.

Read & Learn

20x Faster

without
deepstash

with
deepstash

with

deepstash

Access to 200,000+ ideas

Access to the mobile app

Unlimited idea saving & library

Unlimited history

Unlimited listening to ideas

Downloading & offline access

Personalized recommendations

Supercharge your mind with one idea per day

Enter your email and spend 1 minute every day to learn something new.

Email

I agree to receive email updates