Fever Charts : Assessing Project Performance

Fever Charts : Assessing Project Performance

CCPM introduces a new type of chart to track projects, The Fever Chart

The fever chart plots the percentage of the Project Buffer that has been consumed against the percentage of the critical chain that has been completed. Progress is plotted as a line graph, giving a running commentary of how the project is performing. This can be applied in program and portfolio levels as well, as a diagnostic tool.

9

60 reads

CURATED FROM

IDEAS CURATED BY

Dissecting the core of this business management novel : Critical Chain Project Management (CCPM) Methodology

Read & Learn

20x Faster

without
deepstash

with
deepstash

with

deepstash

Personalized microlearning

100+ Learning Journeys

Access to 200,000+ ideas

Access to the mobile app

Unlimited idea saving

Unlimited history

Unlimited listening to ideas

Downloading & offline access

Supercharge your mind with one idea per day

Enter your email and spend 1 minute every day to learn something new.

Email

I agree to receive email updates